石油化工设备技术 ›› 2023, Vol. 44 ›› Issue (3): 7-12.doi: 10.3969/j.issn.1006-8805.2023.03.002

• 静设备 • 上一篇    

浅谈大型低温储罐三层罐壁板安装施工技术

胡绍辉   

  1. 中石化第四建设有限公司,天津 300270
  • 收稿日期:2023-03-03 接受日期:2023-04-30 出版日期:2023-05-15 发布日期:2023-06-06
  • 作者简介:胡绍辉,男,2004年毕业于天津科技大学机械设计制造及自动化专业,工学学士,长期从事石化建设施工管理工作,现任副总工程师、储运工程公司经理、党委副书记,高级工程师。

On Installation and Construction Technology of Large-scale Cryogenic Storage Tanks with Three-layer Tank Wall Plate

Hu Shaohui   

  1. SINOPEC Fourth Construction Co., Ltd., Tianjin, 300270
  • Received:2023-03-03 Accepted:2023-04-30 Online:2023-05-15 Published:2023-06-06

摘要: 随着国家对化工材料需求的不断增加,常规的球罐储存容量已经不能满足装置生产周转需求,而钢制低温全容罐因具有占地小、储存量大、安全高效、建造周期短、造价低等优点,已成为化工装置存储烯烃的优选方式。其安装工艺对储罐整体施工的进度、安全、质量控制管理等影响显著。文章以10万m3钢制低温全容罐为例,主要介绍了三层罐壁低温储罐壁板正装法施工工艺,具体阐述了三钢低温储罐外罐壁板、中间罐壁板、内罐壁板的安装施工技术。该技术可为同类储罐的安装提供借鉴与参考。

关键词: 低温储罐, 三层罐壁, 安装技术

Abstract: As the national demand for chemical materials continues to increase, the storage capacity of conventional spherical tanks can no longer meet the production turnaround needs of the device. The steel cryogenic full-containment tank has become the preferred way for chemical plants to store olefins owing to its advantages of small footprint, large storage capacity, safety and efficiency, short construction cycle and low cost.Its installation process has a significant impact on the overall construction schedule, safety and quality control management of the storage tanks.Taking the 100,000 m3 steel cryogenic full-capacity tank as an example, this paper mainly introduces the construction process of installation in regular order for the wall plate of cryogenic tanks with three-layer tank wall. It specifically describes the installation and construction technology of the outer tank wall plate, the intermediate tank wall plate and the inner tank wall plate of the trimetallic wall cryogenic storage tank. This technology can provide reference for the installation of similar storage tanks.

Key words: cryogenic storage tank, three-layer tank wall, installation technology